Avondale · 2025

A 1926 frame house taken back to studs

Every system in the house was original or close to it. The owners wanted to keep the street elevation exactly as it was and change everything behind it.

Scope
Whole-home renovation, rewire, rear addition
Budget
$412,000 (sample figure)
On site
38 weeks
Size
2,240 sq ft, plus a 340 sq ft addition
House
Built 1926

Before and after

A 1926 frame house taken back to studs, before work started
A 1926 frame house taken back to studs, finished
BeforeAfter

Drag the handle to compare. Photographs are illustrative for this demo site.

The brief

What they came to us with

The house had been divided into two units in the 1960s and never properly put back. There were two kitchens, four exterior doors that no longer made sense, and a 60 amp service feeding cloth-wire branch circuits.

The owners, a family of four moving from out of state, wanted a single-family plan with four bedrooms, a usable rear entry off the parking pad, and the front elevation untouched because the house sits inside the historic district.

What we did

  • Full rewire, new 200 amp service and meter can, coordinated with the utility
  • New mechanical system after a Manual J on the revised plan, with a second zone for the upstairs
  • Bearing wall removal between the front rooms, with a flush steel beam and a new footing under each column
  • 340 square foot rear addition housing a mud entry, laundry and a bathroom
  • Heart pine floors lifted, re-laid over sistered joists and refinished
  • Plaster repaired where sound, replaced with board where it was not
  • Original front windows repaired and weatherstripped, rear openings replaced to current design pressure

What made it difficult

Historic review

The rear addition and the replacement rear windows needed a certificate of appropriateness. We submitted with the street elevation unchanged and the addition set back from the side wall, and it was approved in the second cycle. Total added time: seven weeks, which we had allowed for in the schedule.

Undersized service

The original 60 amp service could not carry the new mechanical equipment, the range or the laundry. The NEC 220.83 calculation on the finished plan came out at roughly 148 amps, so 200 amp service was the clear answer, and the utility drop had to be relocated to clear the addition roof.

Floor framing

Joists over the crawl had deflected up to an inch and a quarter over the span. We sistered the full length rather than shimming the top, because the heart pine floor was going back down over it.

Two kitchens, one drain

Removing the upstairs kitchen meant abandoning a drain line inside a wall we were keeping. We capped it below the floor and re-vented the remaining bathroom group rather than leaving a dead leg.

How it finished

  • The street elevation is unchanged, which is what the district wanted and what the owners wanted.
  • The finished plan reads as one house again, with a rear entry that takes the real traffic.
  • Energy use dropped noticeably after the envelope and mechanical work, though we do not publish a figure we did not measure over a full year.

They told us about the historic review in the first meeting instead of after we had paid for drawings. That one thing saved us months.

Priya and Dev RaghunathanAvondale, whole-home renovation

More from the archive

Three other jobs

Start where every one of our projects starts